Projects

Our Projects

Sundram Fastners

  • Provided Cost effective Retrofit Solutions for M/s.Sundram FASTNERS, Pondicherry within 18 Hrs we completed 5 nos English Electric ACB to 5nos SIEMENS ACB within Short period .

  • Revamping 07 Numbers of Power Distribution Board Solution provided for M/s.Sundram FASTNERS, Pondicherry, Old Easun to New Tailored made PDB.

  • The furnace electrical revamping project was completed in 7 days, including the tasks of design, manufacture, supply, and installation carried out to restore the electrical supply to the furnace at M/s.Sundram Fastners, Pondicherry. the work includes FURNACE Panel with LV Busduct, Full MS Structural and Tray Work, along with 525 meters of 3.5Cx300Sq.mm LV Cable Laying and Termination

JTEKT India Limited,

  • Completed pre-fabricated 6 numbers of retrofit solutions to minimize the downtime for M/s.JTEKT India Limited, Chennai and done within 24Hrs.

  • Provided the Energy Management Solutions (EMS) with Elmeasure Software for M/s.JTEKT Limited, Chennai, Total 65 new meters and CTs with communication cable; and completed the installation including commissioning

  • New 11kV 03 VCB Panel and 01 Single VCB Panel Project done at M/s.JTEKT Limited, Chennai, includes Design and Supply of New 11kV Panel.

IIT Madras Research Park

  • Project done at M/s.IIT Madras Research Park, Chennai includes supply, installation, and testing of 4CX400sq.mm UG Power Cable 470 meters from MLCP substation to battery container cabling arrangement work completed within 2 days.

.

JTEKT Limited, Chennai

Provided the Energy Management Solutions (EMS) with Elmeasure Software for M/s.JTEKT Limited, Chennai, Total 65 nos of New Meters & CTs with Communication cable and Completed the Installation & Commissioning.

Other Projects

Sundram Fastners

Revamping Power Distribution Board Solution provided for M/s.Sundram FASTNERS, Pondicherry,07 nos of Old Easun PDB to New Tailored made PDB.

Fairfield by Marriott Hotel

  • Restoration of Flooded MV Panels at M/s.Fairfield by Marriott Hotel ,Chennai Work was finished and the hotel’s power supply was restored in less than 48 hours.

  • A MV panel installation project at M/s. Fair Field Marriott OMR Road, Chennai, the project was completed in 15 days, starting with the removal of the old panel and replacing a new panel and rerouting the old cable and connecting with the new panel; all work was perfectly completed without interfering with hotel operations or power outages. Including drawing approval of Tamil Nadu CEIG

VIRTUSA Consulting Services Pvt, Limited

  • New Single 11kV VCB Panel Installation works at M/s.VIRTUSA Consulting Services Pvt, Ltd.,Chennai. The task was completed in eight hours and involved removing the old panel, installing the new VCB panel, and includes testing.